Plan check corrections are written instructions from the plan reviewer identifying elements that don’t comply with applicable codes or that require additional information. Receiving corrections is normal — not a failure. The correct process: review each correction against the cited code section; prepare revised drawings or additional documentation to address every comment; resubmit the complete revised package promptly (not incrementally, which extends the correction cycle); repeat until all corrections are resolved and the permit is issued. For corrections that appear to reflect code misinterpretations, the appropriate response is a written code interpretation request to the building official — not passive compliance that may produce a non-compliant result. RainFire Builders responds to corrections promptly and completely, and advocates through the appropriate process when warranted.